Date09/06/2023
On Duty Officer's NameJoe Wilcox
Shift on DutyShift B
StationStation #1
Change PartnerShift A
Change Partner's NameTanner Orth
Log Information
No Action Needed:

SQ1, Q2, Q3, L4, E2 were all pump tested and passed

In regards to the 2 sections of 1 3/4 hose on R7 I was informed that was the chiefs call. Have no further information on the matter

A 4gas monitor was placed in R42 to investigate a possible exhaust leak. It was found that it did in fact reach up to 9 PPM CO in the cab. An email has been sent to the chiefs to inform them of the issue

Styrofoam cups, paper towels, and blue shop towels were ordered

Action Needed:

Need to decide what needs to be kept or thrown away in the pile of stuff on the west wall of ST.1. B-shift wants nothing so now for the other two shifts to decide.