DESCRIPTION:

Improvement of the intersection of North Broadway Street (U.S. 69 Highway) and 20th Street by partial removal of the existing pavement, drainage improvements, curb and gutter, and incidental construction relating to the improvement, easement and right-of-way acquisitions, widening 20th Street both east and west from said intersection, five (5) lanes of paving on Broadway Street being a distance of 420 feet to the north and 350 feet to the south of said intersection and three (3) lanes of paving on 20th Street being a distance of 300 feet to the east and 410 feet to the west of said intersection to provide left turn lanes, pavement marking, surveying, sidewalks, upgraded traffic signals, storm drainage improvements, water lines, sanitary sewer lines, utility relocation, and design and construction engineering. 

[NOTE:  Storm sewer improvements associated with the project will be expanded to 21st Street to alleviate storm drain problems at the intersection of 20th and Broadway.  The water and sewer lines at the intersection of 20th and Broadway are in conflict with the storm sewers and need to be relocated/replaced.]

AUTHORIZING RESOLUTION:

Approved 04/24/12
(Authorize Project, Temporary Notes and G.O. Bonds Not to Exceed $1,300,000)

ESTIMATE OF PROBABLE COST:

$1,300,000

FUNDING SOURCE:

KDOT Grant (Federal-Aid HSIP Funding) 90% State/10% Local Max. $800,000

Basic Project (Eligible Portion)   $1,185,927
KDOT Share  $800,000
City Share  $385,927
  Breakout of City Portion  
  Storm Sewer Costs $188,425
  Street Costs $197,502
Water Line Costs  $250,000
Sewer Costs $38,000
Additional Storm Sewer Costs $365,000
Right-of-Way Allowance $75,000
Preliminary Engineering  $66,551
Total City Share    $1,180,478

Revenue from water/wastewater utility will be pledged for payment on the bonds issued for the water line and sewer line replacement.
Revenue from the stormwater utility will be pledged for payment on the bonds issued for the storm sewer improvements.

DESIGN CONSULTANT:

Professional Engineering Consultants, PA
902 S. Broadway
Pittsburg, Kansas 66762

Contact Person:
      
Bruce Remsberg
(620) 235-0195 - Mobile

Contract Amount:
$68,997          (includes $14,085 Utility Realignment and Replacement Design and $2,436 Preconstruction Work reviewing shop drawings and equipment submittals)

BID LETTING:

May 22, 2013
[Fiscal Years 2012-2013 (October 2011 through September 2013)]


STATUS UPDATES: