7th Street Storm Sewer Replacement

 Click here for the interactive Project Map

DESCRIPTION: Replacement of the collapsed arch brick storm sewer on 7th Street west of Taylor Street to include the installation of a double 8’ x 5’ RCB storm sewer and associated street repairs.
AUTHORIZING RESOLUTION: NOT NECESSARY SINCE PROJECT IS AN EMERGENCY.
FUNDING SOURCE: 2012 Budget – Stormwater Utility
ENGINEER: City Engineer Contract
[Professional Engineering Consultants]
902 S. Broadway
Pittsburg, Kansas 66762

Contact Person:
Bruce D. Remsberg, P.E.
(620) 235-0195 - Office
(620) 249-6438 – Mobile

BID LETTING: May 15, 2012
CONTRACTOR: Freddy Van’s, Inc.
2513 E. 4th Street
Pittsburg, Kansas 66762

Contact Person:
Rusty VanBecelaere
(620) 231-7166 - Office
(620) 249-4317 - Mobile

CONTRACT AMOUNT: $125,847.10
NOTICE TO PROCEED: TBD

Substantially Completion:45 calendar days
Final Completion:65 calendar days

LIQUIDATED DAMAGES: $600 Per Calendar Day
STORM SEWER MATERIALS: Purchase of materials for the replacement of the collapsed arch brick storm sewer.  Includes 4 each – precast type 22 inlets; 1 each – area inlet; 30 LF – 18” RCP storm sewer; 64 LF – 30”x19” RCPHE storm sewer; and 140 LF – 8’x5’ RCB storm sewer.
BID LETTING: April 24, 2012
SUPPLIER: Scurlock Industries
P.O. Box 257
N. Miami, OK 74358
PURCHASE AMOUNT: $36,654.50

STATUS UPDATES: